Floor restoration work – De Meerkamp Swimming Pool
Phased floor repairs at De Meerkamp Swimming Pool will take place from January 19 to February 15, 2026. Below, you can read about the changes involved, week by week and pool by pool.
Target group pool – Week 4 (January 19 to 25, 2026)
- Replacement of the floor in the disabled toilets
- (the disabled toilet and shower room remain accessible)
- Showers closed due to sealing, grouting and drying
- Locker rooms remain open
- Access to the target group pool via the cloakroom of the competition pool
Competition pool – Week 5 (January 26 to February 1, 2026)
- Last group changing room (seen from the reception) closed due to replacement of the tiling
- Showers and toilets closed due to sealing, grouting and drying
- Passage from the changing rooms to the competition pool closed
- Walking route to the competition pool via the target group pool and the wave pool
Wave Pool – Week 6 (February 2-8, 2026)
- Showers closed due to sealing, grouting and drying
- Parts of the platform closed off due to joints, sealing and drying
- Passage through the cloakroom of the competition pool
This week, the platforms in the competition pool and instruction pool will also be sealed and grouted. Drying time will then be required. This work will be carried out in phases to ensure the pools remain accessible.
When work is being done at the starting blocks, we request that you start on the other side of the competition pool.
Wave Pool – Week 7 (February 9-15, 2026)
Toddler pool and platforms: parts of the platform closed off due to joints, sealing and drying
During the work, work will be carried out in a tent. Nevertheless, it may be dusty in the pool.
We apologize for the inconvenience and thank you for your understanding.