A larger swimming pool, new opportunities, and a new workplace for AmstelveenSport. With the expansion of De Meerkamp swimming pool, Amstelveen has gained a modern and multifunctional swimming pool. The new pool has now been in use for almost a year. Time to look back on the project: from the initial plans and construction to the festive inauguration.

Why an expansion?

Swimming pool De Meerkamp was being used increasingly intensively. Due to the growth in the number of visitors, swimming lessons, clubs, and other activities, there was a need for additional swimming facilities. Therefore, the municipal council decided to expand the swimming pool with a new pool.

A versatile 21 by 25 meter pool was chosen. Thanks to the movable floor and flexible partition wall, the pool can be used for various purposes. For instance, it accommodates swimming lessons and instruction, as well as competitive swimming and activities of water sports clubs.

A new location for AmstelveenSport

The construction of new offices for AmstelveenSport was also part of the project. The organization was growing, and the existing accommodation in the small building behind De Meerkamp was outdated and offered insufficient space. With the new construction, AmstelveenSport gained a modern and future-proof workplace, right next to the swimming pool.

From design to construction

The design of the extension was developed under the leadership of OLCO by a multidisciplinary project team consisting of Slangen + Koenis (architect), BBP (installations), Noorman (building physics), and WSP (structural engineering).

The first preparatory work began in the autumn of 2023. At the end of January 2024, the first pile was driven into the ground, and with that, the expansion increasingly took shape.

The construction was an important milestone for De Meerkamp and AmstelveenSport. Step by step, the new swimming pool was realized, while work on the new offices was being carried out simultaneously.

You can also follow the construction via the Construction App from construction company Vink Bouw

Progress on the expansion of De Meerkamp swimming pool

  • Spring/Summer 2023
    In the summer, after the construction sign was placed, the first thing that was moved was the trees around the current bicycle shed to the rear of the lawn at the Startbaan. A new forest strip is being created there.
  • Week 47 – November 20, 2023
    Moving the bicycle shed. This was to the left of the entrance and will now be on the right side of the building. The bicycle shed must be moved so that construction traffic can access the outside area. The next step is to make the outside area ready for construction.
  • Week 50 – December 11, 2023
    Preparing the outdoor area for construction.
  • Week 3 – January 16, 2024
    Excavation work in connection with sewerage.
  • Week 7-8-9 – February 12 to March 1, 2024
    Placing the sheet piles.
  • Week 10-11-12-13 – March 2 to 30, 2024
The large scaffolding for the sheet piles is being removed. Some of the old changing rooms have been demolished.
  • Week 14 & 15 – April 1 to 14, 2024
The excavation of the construction pit has started. It will take about 4 weeks until the first piles are driven. From that moment on, we will work towards the pouring of the first floors.
  • Week 19 – May 6-12, 2024

The deepest point of the excavation of the construction pit has been reached. In just over a week, it will be dug empty. Then the piles will be cut; the first concrete for the floors will be poured at the end of May. This week, a drone filmed the construction site and the enormous construction pit and its depth can be clearly seen. 

  • Week 20-21 – May 13 to 26, 2024
  • Week 23-24 – June 3 to 16, 2024

Thursday 13 June 2024 the first concrete was poured with a concrete pump with a 47-metre arm. This is the foundation for the offices. The concrete will be poured in the pool shell at the beginning of July.

  • June 2025

We're moving forward in time. The work is progressing according to plan. The roof is now in place. Work is underway in the area where the changing rooms, lockers, and showers will be located, as well as on the hinged wall and movable floor in the pool. Soon, the pool will be filled, and the water quality technology will be thoroughly tested.